News

Truesdale terminates Chapter 100 agreement with Refresco

Posted

A deal with a corporate partner that Truesdale city officials were cautiously optimistic could revitalize a local bottling facility when they approved it four years ago will end next month.

After receiving a letter last month from international bottling company Refresco Beverages Inc. seeking to terminate its Chapter 100 agreement with the city, the Truesdale Board of Aldermen approved an agreement to do so at their Thursday, Nov. 12 meeting.

Refresco took over the former Coca-Cola plant in Truesdale in 2021. “That plant has went from Coke to Pepsi, back to Coke, and then to Refresco, over the years,” Mayor Jerry Cannon told the Record.

Although Cannon was an alderman, rather than mayor, and opposed granting the personal property tax abatement to Refresco at the time, the city nonetheless approved a Chapter 100 agreement with the company in late 2022. Refresco was seeking the abatement in connection with a $22 million investment in a new bottling line for the energy drink company Prime. 

In early 2023, then-Gov. Mike Parson hailed Refresco’s investment in Truesdale as “another testament to our state’s ability to provide the foundation for success that companies need.”

Those advocating for the tax abatement at the time also included Steve Etcher with the Greater Warren County Economic Development Council, who said job creation from Refesco’s investment was “going to create $4 million in payroll that’s going to be felt throughout the community,” according to previous Record reporting.

By 2024, however, Refresco had filed a lawsuit against Congo Brands Procurement LLC and Prime Hydration LLC over complications in plans for bottling the energy drinks at the Truesdale plant. By the end of that year, Refresco was out of compliance with its agreement with the city, meaning it had to revert to paying its full tax obligation.

Refresco has paid its full tax obligation for 2024 and 2025, according to city officials.

When Refresco first acquired the Truesdale plant, the company initially inherited a tax abatement from when it was a Coca-Cola facility, Cannon said.

“And then when Refresco asked for an abatement to build a new production line, they did get an abatement from the city under certain conditions. First of all, the abatement would stagger down as years go by, and also it would not be at the same level as what they’d gotten previously. We wanted Refresco to know that we want them in Truesdale, we value them employing people, and we think of them as a big part of our community,” he said.

“However, we also realize that a tax burden has to be there for infrastructure, for ambulance and fire, for the school, so it was contentious when we were pretty much forcing them into a position that no other board and mayor had before with the latest agreement, where we said no more than a 50 percent abatement, and then it would stagger down to where they were back to paying their full tax burden,” Cannon added.

Refresco was required to hire and maintain 40 full-time employees, a goal that the company believed was realistic at the time.

“Then came the lawsuits,” Cannon said. “They thought they had a contract with Logan Paul and Prime. That fell through when Logan Paul decided to take his business elsewhere, even though he had a contract with them.”

The city revised its Chapter 100 agreement with Refresco, reducing the amount of full-time staff it had to hire and retain in Truesdale from 40 down to 30, and first gave it a deadline of October of last year to comply. That was then extended to this October, but the company was still unable to meet the requirement.

Cannon noted that if Refresco had been able to meet the October deadline, the abatement, which had already been lowering each year, would only have had one year left to go anyway.

“But they could have one year, basically, of an abatement, if they were able to hire and retain those people, and so they couldn’t, so we’re now terminating the agreement,” he said.

The termination agreement that the Truesdale Board of Aldermen approved Nov. 12 is effective Dec. 1.

“You guys have a copy of that, or saw a copy of that, I hope. It’s just basically acknowledging that they know that it’s over,” Cannon said. “That’s the bottom line of it.”

Cannon said there was a silver lining to the Chapter 100 agreement coming to an end, which was an improved relationship between the city and the company. Refresco has shown an increased willingness to help out with community events, he said, supporting efforts such as donating bicycles to give away at Christmas.

“There’s just different things that they’ve all of the sudden done that they didn’t do before, and, you know, the communication is so much better,” Cannon said.

“Before, it was almost impossible to get a hold of anyone with any kind of standing with their company, and now I can message their plant manager and he will get right back to me. So I think it has opened up a new day of partnership and good communication. I think there’s a lot of positives.”


X